You need to take care of time to market. If time and cost are fixed it means scope is variable. Here the emphasis is what best we can deliver within available time and cost. Here we seriously think about what really matters to us and we deliver accordingly.How come TIME & COST could be fixed since the Project is Uncertain ? Are we talking about ITERATION CYCLE FIXED TIME & COST?
How come TIME & COST could be fixed since the Project is Uncertain?
- seema.sonkiya
- Expert
Post
How come TIME & COST could be fixed since the Project is Uncertain?
Got the following question:
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Post
Re: How come TIME & COST could be fixed since the Project is Uncertain?
Dear Miss Seema,
Can we annotate your above concept in my following scenario?
"Suppose, if we have got a budget of 1,000$ for an iteration which is of 30 days, and after delivering 100% cost, but still have more days to review product demo / close the iteration, can we close the iteration by keeping in mind that whatever has intended, it has achieved?
or, we again look at prioritized backlog, to select more use stories, to fill up the remaining bucket size or days, if we do that, we would definitely be incurring more cost than planned (fixed cost) ?
please put some light on it?
Can we annotate your above concept in my following scenario?
"Suppose, if we have got a budget of 1,000$ for an iteration which is of 30 days, and after delivering 100% cost, but still have more days to review product demo / close the iteration, can we close the iteration by keeping in mind that whatever has intended, it has achieved?
or, we again look at prioritized backlog, to select more use stories, to fill up the remaining bucket size or days, if we do that, we would definitely be incurring more cost than planned (fixed cost) ?
please put some light on it?
- seema.sonkiya
- Expert
Post
Re: How come TIME & COST could be fixed since the Project is Uncertain?
It all depends on what is important. The Product Owner decides if remaining features are critical for implementation? There is no fixed rule, we don't do things for sake of doing, if there is a value then we can complete remaining features.
The idea was if you have a limited budget, then plan things which can give the best value in this budget. Also if intended is achieved then no need to develop other things for the sake of doing.
The idea was if you have a limited budget, then plan things which can give the best value in this budget. Also if intended is achieved then no need to develop other things for the sake of doing.
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com