Forum banner

Stakeholder engagement

Exclusive forum for iZenBirdge PMP® clients
manishaagarwal
Posts: 15
Joined: Fri Aug 25, 2017 4:18 am

Stakeholder engagement

Mon Jan 16, 2023 11:01 am

Below is the question:

You were monitoring one core stakeholder’s engagement level, and you found he was becoming neutral from supportive; you spoke to the stakeholder and found that he is not finding enough opportunity to engage with the project team, what should you do next?
1. Raise an issue.
2. Make changes in stakeholder engagement strategy documented in stakeholder engagement plan.
3. Raise a change request.
4. Call a meeting with your project team members.

The correct answer to this point 4. However, I think in order to engage the stakeholder we should make change in stakeholder engagement strategy. How will meeting team members be helpful? Can someone throw more light on this.

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 5 guests