I have got this question wrong, please explain
User testing on the last product release revealed low user interest in certain features that required significant effort to develop.
What can the agile team do to prevent this disparity in the future?
Ask the product owner to ensure all stories in the backlog support the product vision
Ensure that user stories in the backlog are broken down into the smallest possible form
Remove all stories from the backlog that are not selected for the Minimal Viable Product
Perform stakeholder analysis to find SMEs who can guide the backlog value ranking process
Solution
The product was released without sufficient user input or prioritization to ensure it has appeal and delivers business value. SME input (for example from marketing or market researchers) can help with ranking the features appropriately. Distractors include vision alignment and story refinement which are normal agile practices but do not address the prioritization and business value problem. The MVP does not target user satisfaction, rather it targets basic functionality to build upon.
Explain Agile based Question
- saket
- Site Admin
Post
Re: Explain Agile based Question
It will be helpful if you have pointed out the confusion since I see the right answer can only be D since option A, B and C are not collaborative in nature. In PMP exam we need to find best answer from the given 4
A. Ask the product owner to ensure all stories in the backlog support the product vision
Non collaborative and we do not know if we are using Scrum here and we have PO
B. Ensure that user stories in the backlog are broken down into the smallest possible form
Breaking the stories does not help finding the priority
C. Remove all stories from the backlog that are not selected for the Minimal Viable Product
Unrelated , the Product backlog has to have all the items and we are not sure if we have MVP release happening or MBI release happening
D. Perform stakeholder analysis to find SMEs who can guide the backlog value ranking process
The only left with and has not reason to get rejected, we need to find right people to join the backlog refinement
A. Ask the product owner to ensure all stories in the backlog support the product vision
Non collaborative and we do not know if we are using Scrum here and we have PO
B. Ensure that user stories in the backlog are broken down into the smallest possible form
Breaking the stories does not help finding the priority
C. Remove all stories from the backlog that are not selected for the Minimal Viable Product
Unrelated , the Product backlog has to have all the items and we are not sure if we have MVP release happening or MBI release happening
D. Perform stakeholder analysis to find SMEs who can guide the backlog value ranking process
The only left with and has not reason to get rejected, we need to find right people to join the backlog refinement