A company’s management is discussing a project request created by one of its managers. but its mangers are uncertain, whether the project is worth the investment. A project manager has been assigned to develop a document to describe the potential benefits in monetary and other aspects. After acceptance of the project request, this document will to be used to track the realization of those benefits.
A.Project business case
B.Benefits management plan
C.Project charter
D.Project statement of work

Answer is A. Why should it not be B? Seems like Benefits management plan is being prepared.
Thanks
mogh
Posts: 5
Joined: Sun Dec 09, 2018 3:36 am

Re: Oliver Lehmann 100- Q 80

Postby mogh Tue Dec 25, 2018 5:44 pm

The project business case is a documented economic feasibility study used to establish the validity of the benefits
of a selected component lacking sufficient definition and that is used as a basis for the authorization of further project
management activities. The business case lists the objectives and reasons for project initiation.