Please help with these questions

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
mogh
Posts: 5
Joined: Sun Dec 09, 2018 3:36 am

Please help with these questions

Postby mogh Wed Dec 19, 2018 3:44 am

1. You joined in the middle of the project as a PM . What of the following document are you sure of updating?

• Charter
• Stakeholder register


2. You are on a project which has a tight deadline and failing to comply will result in penalties. What type of contract should you do with a supplier providing a critical element required to complete the project?
• CPAF
• FPIF

3. During initial planning stage a Functional Manager argues why his department was not given any information on project ? You think his department does not require this info. What document should you use to confirm your statement?

• Charter
• Stakeholder register
• Stakeholder engagement Plan
manishpn
Expert
Expert
Posts: 2610
Joined: Sat Jan 04, 2014 3:55 pm

Re: Please help with these questions

Postby manishpn Wed Dec 19, 2018 2:01 pm

mogh wrote:1. You joined in the middle of the project as a PM . What of the following document are you sure of updating?

• Charter
• Stakeholder register

Nothing can be said with surety with one line question, but Charter update is less probable


2. You are on a project which has a tight deadline and failing to comply will result in penalties. What type of contract should you do with a supplier providing a critical element required to complete the project?
• CPAF
• FPIF

FPIF , since award based contracts are always subjective


3. During initial planning stage a Functional Manager argues why his department was not given any information on project ? You think his department does not require this info. What document should you use to confirm your statement?

• Charter
• Stakeholder register
• Stakeholder engagement Plan



Stakeholder register and engagement plan are usually not to be shared as is with stakeholders as they may contain sensitive information, so it has to be charter
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
mogh
Posts: 5
Joined: Sun Dec 09, 2018 3:36 am

Re: Please help with these questions

Postby mogh Wed Dec 19, 2018 2:12 pm

Many thanks Manish
mogh
Posts: 5
Joined: Sun Dec 09, 2018 3:36 am

Re: Please help with these questions

Postby mogh Sat Dec 29, 2018 12:11 am

Your project sponsor has asked for an EAC and has told you that he wants you to use ETC work considering CPI and SPI factors. You know that this formula assumes which of the following?

A. There is a positive cost performance to date.
B. There is a negative cost performance to date, and the project schedule must be met.
C. The project schedule has slipped and must be corrected.
D. There is a positive cost performance to date, and the project schedule must be met.
manishpn
Expert
Expert
Posts: 2610
Joined: Sat Jan 04, 2014 3:55 pm

Re: Please help with these questions

Postby manishpn Tue Jan 01, 2019 5:34 am

mogh wrote:Your project sponsor has asked for an EAC and has told you that he wants you to use ETC work considering CPI and SPI factors. You know that this formula assumes which of the following?

A. There is a positive cost performance to date.
B. There is a negative cost performance to date, and the project schedule must be met.
C. The project schedule has slipped and must be corrected.
D. There is a positive cost performance to date, and the project schedule must be met.


It will be option B
Usually when project is over budget and behind schedule and project has t be completed on time, we need to calculate ETC considering both SPI and CPI
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/