Q. During execution PM is testing the product for every added functionality to avoid the future risk for every phase. what process is PM actually performing ?
A. Quality management plan
B. Planning Quality
C. Control Quality
D.Manage Quality
Quality
Re: Quality
Satya wrote:Q. During execution PM is testing the product for every added functionality to avoid the future risk for every phase. what process is PM actually performing ?
A. Quality management plan
B. Planning Quality
C. Control Quality
D.Manage Quality
This is simple try it and lets discuss after you attempt
Re: Quality
With an added risk option, it could have been more interesting.
Control Quality.
Control Quality.