Change control

Postby Satya Fri Nov 02, 2018 2:20 pm

Context is:

A project was about to get delivered but got stuck with an issue at the final stage .This is resolved by the team member that added a good functionality to the project but they did not perform the integrated change control process.
what should a PM do?

a. Team member needs to be fired
b. Raise the issue
c.Create a Change request
d. deliver the project
manishpn
Expert
Expert
Posts: 2572
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change control

Postby manishpn Mon Nov 05, 2018 10:21 am

Satya wrote:Context is:

A project was about to get delivered but got stuck with an issue at the final stage .This is resolved by the team member that added a good functionality to the project but they did not perform the integrated change control process.
what should a PM do?

a. Team member needs to be fired
b. Raise the issue
c.Create a Change request
d. deliver the project


I will go with option B, raising this as an issue that process was not followed and then take next steps
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Satya
Posts: 13
Joined: Mon Oct 29, 2018 1:17 am

Re: Change control

Postby Satya Mon Nov 05, 2018 5:09 pm

Thanks Manish,
So , you mean we raise an issue and close it as we need to notify genuinely .. ? or is there any other procedure to handle these situations.
PCS
Posts: 10
Joined: Thu Oct 25, 2018 8:50 am

Re: Change control

Postby PCS Tue Nov 06, 2018 9:47 am

I agree with Manish.
From the sentence about to be delivered, we can think this happening during Control Quality Process( Verify Deliverable -issues are found and resolved) and before Validate Scope(deliverable accepted/signoff).
During quality control, if any issue found a defect/issue is raised and during defect addressing, we fix the issue if its not violating baselines(scope, schedule, cost, quality). If fix violating the baselines, we raise the CRQ and due process to complete the CRQ.

If its time to go for Validate Scope before fixing the issue/CRQ, during the discussions with customer, it needs to be appraised.

Regards,
PCS
Last edited by PCS on Sat Nov 10, 2018 8:42 pm, edited 1 time in total.
Satya
Posts: 13
Joined: Mon Oct 29, 2018 1:17 am

Re: Change control

Postby Satya Fri Nov 09, 2018 8:57 pm

Thanks for elaobaration PCS, these minutes are eating away the time in choosing the answer.