Assessment of other Risk Parameters - Qualitative Risk Analysis

Sun Oct 21, 2018 2:51 am

Dormancy of a risk:
High dormancy of risk (Risk materialized but takes longer time to impact; low Dormancy of Risk - risk materialized but takes lesser time to impact.

which of them should be prioritized?

Thank you.
manishpn
Expert
Expert
Posts: 2846
Joined: Sat Jan 04, 2014 3:55 pm

Re: Assessment of other Risk Parameters - Qualitative Risk Analysis

Thu Oct 25, 2018 7:33 pm

salman_2005 wrote:Dormancy of a risk:
High dormancy of risk (Risk materialized but takes longer time to impact; low Dormancy of Risk - risk materialized but takes lesser time to impact.

which of them should be prioritized?

Thank you.

there is no general black and white answer to this.
prioritization depends on many factors like Strategic impact, manageability, potential time of risk occurrence,Propinquity etc
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/