Which of the following best describes Plan Stakeholder Engagement process?

a. Creating and maintaining relationships between the project team and stakeholders
b. Preventing negative stakeholders from derailing the project
c. Striking a balance between stakeholder needs and project needs
d. Focusing on from the creation of the stakeholder management strategy

answer A (source edwel.com) page 400 PMBOK5

in my opinion : answer should be C- page 522 PMBOK6 please correct
kunwar
Posts: 15
Joined: Fri Dec 01, 2017 10:28 am

Re: plan stakeholder engagement

Postby kunwar Mon Jul 09, 2018 11:56 am

hi team,
Please clarify
:(
manishpn
Expert
Expert
Posts: 2572
Joined: Sat Jan 04, 2014 3:55 pm

Re: plan stakeholder engagement

Postby manishpn Mon Jul 09, 2018 5:00 pm

if you need faster response post in exclusive section

I would suggest you refer to PMBOK6 based questions ,

Based on options provided first 3 are true, to certain extent, option B is also subset of the overall stakeholder engagement strategy though Project does not only focus on negative stakeholders, it would be better if you can post what justification the mock that you are referring to has provided for option A


a. Creating and maintaining relationships between the project team and stakeholders
b. Preventing negative stakeholders from derailing the project
c. Striking a balance between stakeholder needs and project needs
d. Focusing on from the creation of the stakeholder management strategy
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
kunwar
Posts: 15
Joined: Fri Dec 01, 2017 10:28 am

Re: plan stakeholder engagement

Postby kunwar Tue Jul 17, 2018 11:00 am

hi Manish/Sakat,

Thank you replying my Query.

but as you know PMP always give all correct answers for a question asked and we need to choose the best suitable answer from the given question.

So can you pl clarify my doubt now
Thanks
Kunwar goyal
manishpn
Expert
Expert
Posts: 2572
Joined: Sat Jan 04, 2014 3:55 pm

Re: plan stakeholder engagement

Postby manishpn Wed Jul 18, 2018 2:23 pm

if I Have to choose best options, it would be A, creating and maintaining relationship with stakeholder is important, option C wont be possible if you dont have good working relation with the stakeholders
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
PCS
Posts: 10
Joined: Thu Oct 25, 2018 8:50 am

Re: plan stakeholder engagement

Postby PCS Thu Nov 08, 2018 11:47 am

It may sound weird. How about option -d . Its the strategy that has all the plans in dealing Option A to C ?
Its the plan in handling all the other situations and executing it in further processes.