Input like ‘Enterprise environmental factor’ and T&T ‘Meetings’ have not been mentioned in the PMBOK for Implement risk response.Similarly, ‘Expert Judgement’ is not specifically mentioned in PMBOK 6 as T&T for Monitor Risk ITTO. We heard Saket mentioning in videos that EEF will be always there..meetings is also needed for every process which we agree.
Question is should we stick to options whatever is written in PMBOK for respective processes or should answer the questions thinking that OPA & EEF (Inputs), Expert Judgement & meetings (T&T) will always be there in all the processes in the exam?
Thanks!
General query
- seema.sonkiya
- Expert
- Posts: 2397
- Joined: Fri Jul 11, 2014 11:57 am
Re: General query
As a paid customer, please post your questions in exclusive area. I am moving there
Thanks & Kind Regards,
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Seema Sonkiya, PMI-PBA Trainer
http://www.izenbridge.com/pmi-pba/online-course/
http://www.izenbridge.com | Email: seema.sonkiya@iZenBridge.com
Re: General query
Awaiting response to my query.
Thanks!
Thanks!
Re: General query
KaurP wrote:Input like ‘Enterprise environmental factor’ and T&T ‘Meetings’ have not been mentioned in the PMBOK for Implement risk response.Similarly, ‘Expert Judgement’ is not specifically mentioned in PMBOK 6 as T&T for Monitor Risk ITTO. We heard Saket mentioning in videos that EEF will be always there..meetings is also needed for every process which we agree.
Question is should we stick to options whatever is written in PMBOK for respective processes or should answer the questions thinking that OPA & EEF (Inputs), Expert Judgement & meetings (T&T) will always be there in all the processes in the exam?
PMBOK is a framework/guidelines and is not a rule book, so if a given process does not have an input which a PM think should be there, that has to be factored in tailoring options,
So when you prepare for Exam, do not stress yourself a lot if you think one of the inputs or T and T is missing in a process in PMBOK, rather focus and channel your energy in getting a logical grip on the process , rest wil follow
Exam does not ask you to memorize any ITTO
Thanks!