Justin is performing actions such as reporting and comparing actual results against project management plan, analyzing performance data and determining if corrective or preventive action should be recommended, documenting all information, gathering and recording project information and monitoring approved change requests. Which process are you performing?

Aren't we monitoring the validated changes here? Approved changes are being analyzed /validated in Control Quality?
manishpn
Expert
Expert
Posts: 2553
Joined: Sat Jan 04, 2014 3:55 pm

Re: Izenbridge ( dynamic) Question on change control

Postby manishpn Sun Dec 17, 2017 8:23 am

need to know full question before i comment
have asked admin to share
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
manishpn
Expert
Expert
Posts: 2553
Joined: Sat Jan 04, 2014 3:55 pm

Re: Izenbridge ( dynamic) Question on change control

Postby manishpn Sun Dec 17, 2017 10:49 am

we do not monitor approved changes in control quality

thanks for pointing that out needs to be rectified
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 2 guests