Which of the following term BEST defines the work needed to develop a product, service, or result?
1) Product scope
2) Scope baseline
3) Scope verification
4) Project scope

Correct ans: 4 : Project scope describes the work that must be performed to deliver a product, service, or result to the stakeholders. Product scope describes the features and functions that characterize a product, service, or result.

My view: best choice should be 2 as it includes Scope base line + WBS + WBS dictionary. Work need to be done for project product should be more detailed in scope base line. isnt it ?
seema.sonkiya
Expert
Expert
Posts: 1848
Joined: Fri Jul 11, 2014 11:57 am

Re: Project Framework [DP4P10] - question # 10

Postby seema.sonkiya Mon Dec 04, 2017 11:14 am

What is the source of the question?

I suggest to post in the relevant section related to the course.

Return to “Questions about Our classes, Online Classes, Webinars, Booking, Payment etc.”

Who is online

Users browsing this forum: No registered users and 0 guests