integration management Q&A

Postby rahul.kanugo Mon Aug 07, 2017 6:57 am

Is the answer justified???
in attachment...thanks in advance
Attachments
integration.PNG
integration management
integration.PNG (230.31 KiB) Viewed 315 times
nazrulq
Contributor
Contributor
Posts: 233
Joined: Sun Feb 26, 2017 6:06 am

Re: integration management Q&A

Postby nazrulq Mon Aug 07, 2017 10:16 pm

I think cancel the project is the least likely to have but at the phase end review, it happens.
komal
Participant
Participant
Posts: 67
Joined: Wed May 31, 2017 4:34 pm

Re: integration management Q&A

Postby komal Tue Aug 08, 2017 3:05 am

According me Option is D is correct, Cost management plan is part of Planning process group and budget can't be measured at each and every phase review, Hence Option D Correct.

Manish, Correct if i am wrong.
manishpn
Expert
Expert
Posts: 2158
Joined: Sat Jan 04, 2014 3:55 pm

Re: integration management Q&A

Postby manishpn Tue Aug 08, 2017 3:33 pm

lets understand close phase -

It is a checkpoint used to validate the completion of the phase, hand over deliverable to operations at the same time is also called as kill point, as the name suggest it is a check on projects business case relevance and if there is a need to kill the project or move on with subsequent phase.

now let understand in what situations do we need additional budget - when there is change in any of the parameters (scope/schedule) which will need additional budget.
IN close phase the discussion is more focused on business case validity of the project and formal completion of a given phase.
When the next phase begins there could be changes during the planning phase impacting the budget.

So while there is a possibility that budget change may happen during the closure of a phase, it is less likely as compared all other options provided
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 233
Joined: Sun Feb 26, 2017 6:06 am

Re: integration management Q&A

Postby nazrulq Wed Aug 09, 2017 4:54 am

Justification is understandable but question has asked for least likely option. Phase end review rarely cancelled the project. Try to mitigate or change anything in terms of budget , scope or schedule etc.
manishpn
Expert
Expert
Posts: 2158
Joined: Sat Jan 04, 2014 3:55 pm

Re: integration management Q&A

Postby manishpn Wed Aug 09, 2017 8:59 am

nazrulq wrote:Justification is understandable but question has asked for least likely option. Phase end review rarely cancelled the project. Try to mitigate or change anything in terms of budget , scope or schedule etc.



As I mentioned above Phase end review is also called kill point and that means a point to cancel the project if business is not valid anymore. So Project cancellation can happen.

project cancellation is not least likely option for sure.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
rahul.kanugo
Beginner
Beginner
Posts: 30
Joined: Tue May 17, 2016 4:42 pm

Re: integration management Q&A

Postby rahul.kanugo Thu Aug 10, 2017 9:47 am

thanks all well explained