Project Staatus

Postby nazrulq Tue Aug 01, 2017 1:48 am

Question : During the completion of project, sponsor asked you the send project updates as record.
CPI= 1 and SPI =.9 which one under following you will give the sponsor as updates of the project.

Answer:

1. The project is completed and on Budget and behind the schedule.
1. The project is not completed and on Budget and behind the schedule.
1. The project is completed and under Budget and behind the schedule.
1. The project is not completed and over Budget and ahead the schedule.

Correct Answer : As SPI is less than 1 project is behind the schedule . I do n't know what is the completion status .
Does it also explains the completion criteria.

Can somebody explain!
Prembalaji
Beginner
Beginner
Posts: 39
Joined: Wed May 10, 2017 1:38 pm

Re: Project Staatus

Postby Prembalaji Tue Aug 01, 2017 2:43 am

The Answer should be - The project is completed and on Budget and behind the schedule.

CPI=1 is "on" budget (not over or under)
SPI=0.9 is behind schedule

Can someone correct me if im wrong
Cheers,
PJ
nazrulq
Contributor
Contributor
Posts: 256
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Staatus

Postby nazrulq Tue Aug 01, 2017 2:52 am

Just want to know where I can get evidence the project is completed!
sm365
Beginner
Beginner
Posts: 26
Joined: Sat Mar 11, 2017 2:24 pm
Location: Saudi Arabia

Re: Project Staatus

Postby sm365 Tue Aug 01, 2017 10:49 am

My answer :: The project is not completed and on Budget and behind the schedule.

Because, we can firmly say project is completed only when SPI = 1. But here SPI is < 1. When it comes to CPI, the project is clearly ON budget.
Mohammed Shabbir
PMP, ITIL Expert
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Wed Aug 02, 2017 7:26 pm

nazrulq wrote:Just want to know where I can get evidence the project is completed!



good question,

first of all remember that when question is focused on earned value management topic , one should remember that SPI of means that project has earned all its value, i.e. the scope is completed and we should assume that project is complete.
CPI=1 only means project is on track wrt budget .

now if you look outside of EVM area, how do we get formal evidence of project completion.

look at the process of close project/phase.
1. approved final product.
2. final closure report which is also signed off by relevant stakeholders.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
komal
Participant
Participant
Posts: 77
Joined: Wed May 31, 2017 4:34 pm

Re: Project Staatus

Postby komal Fri Aug 04, 2017 5:24 pm

Don't we get an idea from Question statement During the completion of project that project is completed. Please clarify
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Fri Aug 04, 2017 6:56 pm

komal wrote:Don't we get an idea from Question statement During the completion of project that project is completed. Please clarify



During the completion of the project does not mean that project is formally completed
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 256
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Status

Postby nazrulq Sat Aug 05, 2017 5:51 am

The Question is given SPI = 0.9 , CPI =1.0 and the closing process group but SPI=.9, the project is delayed not as per closing date. Project Manager is giving earn value management status to the sponsor near to closing.
It is not wise to call Project is completed as SPI< 1 but on budget.

Manish there are questions in PMP exam and now those as not so simple as presented in Rita or PMstudy or Christopher Scordo and Izenbridge.
Maximum 85 % to 90% what PM should do. If you can give a break down sequence of PM roles in every process and combination between quality and risk.
Project closure and procurement closure!

Manish can you briefly explain.
komal
Participant
Participant
Posts: 77
Joined: Wed May 31, 2017 4:34 pm

Re: Project Staatus

Postby komal Sat Aug 05, 2017 7:54 am

Then how cam i find project is completed or not , if i am not wrong from SPI =0.9 as shows project is behind schedule? Please share your views and clarify.
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Sat Aug 05, 2017 11:25 am

kindly see my response in above in this thread
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
komal
Participant
Participant
Posts: 77
Joined: Wed May 31, 2017 4:34 pm

Re: Project Staatus

Postby komal Sat Aug 05, 2017 3:18 pm

I could not get clarification, can you please put shadow again "How to justify project is completed" ?
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Sun Aug 06, 2017 4:40 pm

komal wrote:I could not get clarification, can you please put shadow again "How to justify project is completed" ?


this is what i have posted before

first of all remember that when question is focused on earned value management topic , one should remember that SPI of means that project has earned all its value, i.e. the scope is completed and we should assume that project is complete.
CPI=1 only means project is on track wrt budget .

now if you look outside of EVM area, how do we get formal evidence of project completion.

look at the process of close project/phase.
1. approved final product.
2. final closure report which is also signed off by relevant stakeholders.
Br,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 256
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Staatus

Postby nazrulq Mon Aug 07, 2017 5:09 am

Please provide book reference!
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Mon Aug 07, 2017 9:05 am

nazrulq wrote:Please provide book reference!


You will not find everything in PMBOK.

if you want PMBOK reference you should look at the outputs of close project process to get clue,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 256
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Staatus

Postby nazrulq Mon Aug 07, 2017 10:13 pm

To pass PMP is difficult as the answers are debatable! I do n't know how the match with PMI-isms.

Thanks.
manishpn
Expert
Expert
Posts: 2353
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project Staatus

Postby manishpn Wed Aug 09, 2017 9:17 am

nazrulq wrote:To pass PMP is difficult as the answers are debatable! I do n't know how the match with PMI-isms.

Thanks.


Dont really understand how this question is related to PMIsm.
I guess you are thinking too much, based on your participation on forum, I believe you are understanding most of the topics/discussion and you should not be worried so much and just focus on conceptual understanding on KA and Processes

I would suggest you participate in next clarification session and we can discuss on this topic.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 256
Joined: Sun Feb 26, 2017 6:06 am

Re: Project Staatus

Postby nazrulq Fri Aug 11, 2017 10:44 pm

Sure. We can discuss!