Postby skommana Fri May 05, 2017 2:46 am

Joe is managing a project having budget of $250,000 and it need to be completed in 10 months. At the time of completion of project, he found that 10% cost of the project is increased because of high material cost and because of delay delivery of material project gets delayed by 10%. Calculate CPI and SPI at the time of project completion.
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Can someone help on this

Postby manishpn Fri May 05, 2017 7:25 am

please try to attempt this question with your own understanding and we can discuss .
for all match and other calculations you should attempt (thats the best way to learn) rather than getting answers/
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Beginner
Beginner
Posts: 30
Joined: Sun Feb 26, 2017 6:06 am

Re: Can someone help on this

Postby nazrulq Wed May 10, 2017 5:41 am

10% time increased = 11 months =EV
10% cost increased = 250 000 * 1.1 =275 000 =AC
SPI =10/11=.91
CPI =250/275=.91
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Can someone help on this

Postby manishpn Wed May 10, 2017 3:28 pm

nazrulq wrote:10% time increased = 11 months =EV
10% cost increased = 250 000 * 1.1 =275 000 =AC
SPI =10/11=.91
CPI =250/275=.91



please read question carefully
Calculate CPI and SPI at the time of project completion.

Now think and answer
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
imranz
Posts: 1
Joined: Thu Aug 04, 2016 2:00 am

Re: Can someone help on this

Postby imranz Fri May 12, 2017 4:54 am

please correct me if I am wrong

BAC = 250000
10% increase in cost means AC = 250000 and 10% of 250000 (25000 extra)
so AC = 275000
EV will remain 250000 because that's what we were suppose to finish so at completion EV = PV = 250000

CPI = EV/AC = 250000/275000 = .909

SPI = EV/PV = 250000/250000 = 1
manishpn
Expert
Expert
Posts: 1923
Joined: Sat Jan 04, 2014 3:55 pm

Re: Can someone help on this

Postby manishpn Fri May 12, 2017 3:29 pm

yes you are correct
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Beginner
Beginner
Posts: 30
Joined: Sun Feb 26, 2017 6:06 am

Re: Can someone help on this

Postby nazrulq Mon May 15, 2017 2:03 am

The Question shouls be cleared of fnishing date. Cost increased by 10% due to material cost and delayed supply.
EV= PV
I think sometimes are not really clear. Hopefully in final PMP it should be mentioned clearly.

Best Regards.