Weighted Milestone Method

Postby Housam Bassal Sun Feb 26, 2017 8:52 pm

Manish,

Could you please explain what is Weighted Milestone Method ? :?
Housam Bassal
Ecuador - Quito
LinkedIn: https://www.linkedin.com/in/housam-bassal-49984357
manishpn
Expert
Expert
Posts: 1809
Joined: Sat Jan 04, 2014 3:55 pm

Re: Weighted Milestone Method

Postby manishpn Tue Feb 28, 2017 6:48 am

its one of the method used for caculating earned vaue.


each milestone is assigned a value which project earns when the milestone is 100% complete.

So at any given day the earned value of the project = sum of values of all milestones which are 100% complete
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist