In terms of the decomposition of requirements on an Agile project the artifact that contains release plans as its first level of decomposition is referred to as a?

A) Product Roadmap
B) Release Backlog
C) Product Backlog
D) Sprint Backlog
seema.sonkiya
Expert
Expert
Posts: 1572
Joined: Fri Jul 11, 2014 11:57 am

Re: Artifact that contain release plan

Postby seema.sonkiya Mon Feb 13, 2017 11:51 am

Please put questions in the open PMI-ACP forum (viewforum.php?f=7) which are not part of the iZenBridge Question Bank. I am moving it there.

Also mention the source of the question, if it is not from the iZenBridge. The source question is: https://www.project-management-prepcast ... uestion-34

Where the option C has Product Roadmap

A product Roadmap is a guidepost which shows how the product will be developed. It is a visual depiction of product releases. It communicates what would be the main components in each release. It is a quick view of release points with the expected functionality. This is a high-level planning tool.

One important point: In Agile we are ready to accept changes, so for planning in each release, you have to go back to the roadmap to check if plan still work or need adjustments.
ashish.jais
Posts: 8
Joined: Mon Dec 05, 2016 8:49 am

Re: Artifact that contain release plan

Postby ashish.jais Tue May 09, 2017 6:11 pm

Question specifically talk about "the artifact that contains release plans "
Why release backlog is not a right answer?

Items shortlisted to be released are move to release backlog.
Is the below hierarchy right(Coarse to granular)?
Backlog-> release backlog->sprint backlog
seema.sonkiya
Expert
Expert
Posts: 1572
Joined: Fri Jul 11, 2014 11:57 am

Re: Artifact that contain release plan

Postby seema.sonkiya Thu May 11, 2017 1:35 pm

Please read the whole sentence as a whole key word:

"artifact that contains release plans as its first level of decomposition"