Question 77
You identified a technical risk in your project and assigned a contingency for that.
Planning contingency reserves is part of which risk response strategy?
A. Active risk mitigation
B. Passive risk avoidance
C. Passive risk acceptance
D. Active risk acceptance
Oliver 175 - 77th Question
- jyotimayank
- Expert
- Posts: 521
- Joined: Mon Mar 09, 2015 6:01 am
Oliver 175 - 77th Question
Jyoti Gupta
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
- catchnithi
- Posts: 1
- Joined: Tue Apr 04, 2017 1:38 am
Re: Oliver 175 - 77th Question
Passive risk acceptance !!
Is right ?.
Is right ?.
- jyotimayank
- Expert
- Posts: 521
- Joined: Mon Mar 09, 2015 6:01 am
Re: Oliver 175 - 77th Question
Hi
The correct answer is option D.
Refer to PMBOK® Guide fifth Edition, page 344 (“accept”).
The correct answer is option D.
Refer to PMBOK® Guide fifth Edition, page 344 (“accept”).
Passive acceptance is a strategy that means no plans are created to try to avoid or mitigate the risk. The team is willing to accept the consequences of the risk should it occur. Acceptance might also mean the project team was unable to come up with an adequate response strategy and must accept the risk and its consequences. Active acceptance include developing contingency reserves to deal with risks incase risk occurs.
Jyoti Gupta
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
Return to “Oliver 175 PMP Questions”
Who is online
Users browsing this forum: No registered users and 2 guests