Oliver 75 - 31st Question

raviganti
Posts: 3
Joined: Wed Mar 30, 2016 6:20 pm

Oliver 75 - 31st Question

Postby raviganti Mon May 02, 2016 2:13 am

Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.
What is the minimum total duration between the milestones A and B?


a. 36 days
b. 37 days
c. 39 days
d. 42 days

What is the correct Answer. Could someone help. I chose the answer as 42 (20+10+5+6) = 41 and then (-2+1) = 42 and i am not sure if this is correct since answer from Oliver's answer sheet shows as B. Can someone explain to this.
Attachments
pmp-ex1.gif
pmp-ex1.gif (3.82 KiB) Viewed 6823 times
User avatar
saket
Site Admin
Site Admin
Posts: 3118
Joined: Sat Dec 07, 2013 10:37 pm

Re: Oliver 75 - 31st Question

Postby saket Tue May 03, 2016 10:06 am

Here you go.
Attachments
20160503_153310.jpg
20160503_153310.jpg (28.9 KiB) Viewed 6815 times
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
User avatar
saket
Site Admin
Site Admin
Posts: 3118
Joined: Sat Dec 07, 2013 10:37 pm

Re: Oliver 75 - 31st Question

Postby saket Wed May 04, 2016 9:13 am

Here is an video on logical relationship

Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “Oliver 75 PMP Questions”

Who is online

Users browsing this forum: No registered users and 4 guests