You are in charge of a project to build a bridge across a river.You are midway through the project.However due to changes in environmental laws the project can no longer proceed and would need to be terminated.Executive management has asked you to document the level of work completed for the project.This would be done in which of the processes ?
A. Project Closure
B. Contract closure
C. Project charter
D. Scope Verification

Answer is D. Do we not initiate project closure once project is declared to be terminated? Please help explain if this is correct answer
manishpn
Expert
Expert
Posts: 2788
Joined: Sat Jan 04, 2014 3:55 pm

Re: Terminated project - document level of work completed

Postby manishpn Sat Nov 02, 2019 5:30 pm

bhavini.barot wrote:You are in charge of a project to build a bridge across a river.You are midway through the project.However due to changes in environmental laws the project can no longer proceed and would need to be terminated.Executive management has asked you to document the level of work completed for the project.This would be done in which of the processes ?
A. Project Closure
B. Contract closure
C. Project charter
D. Scope Verification

Answer is D. Do we not initiate project closure once project is declared to be terminated? Please help explain if this is correct answer


This is a good quality question,
The question says Management wants to know how much work is completed, the process which confirms the validity of the deliverable is Validate Scope, one of the output of this process is accepted deliverable, which serves as input to Close project or phase process.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
bhavini.barot
Posts: 15
Joined: Mon Apr 15, 2019 5:34 pm

Re: Terminated project - document level of work completed

Postby bhavini.barot Mon Nov 04, 2019 5:53 pm

This makes sense Manish. Thank you.

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 5 guests