Indentify Stakeholders Process - Change Request

Postby bhavini.barot Mon May 06, 2019 2:55 am

Change request is one of the outputs for Identify Stakeholder process. Can you please explain (if possible with example) how can change request be generated in process of identifying stakeholders?
manishpn
Expert
Expert
Posts: 2656
Joined: Sat Jan 04, 2014 3:55 pm

Re: Indentify Stakeholders Process - Change Request

Postby manishpn Mon May 06, 2019 11:19 am

bhavini.barot wrote:Change request is one of the outputs for Identify Stakeholder process. Can you please explain (if possible with example) how can change request be generated in process of identifying stakeholders?





I give you a hint from PMBOK
'Identify Stakeholders is the process of identifying project stakeholders regularly and analyzing and documenting
relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on
project success.'


read the above statement, can you find the need for a CR as an out put for this process?
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
bhavini.barot
Posts: 3
Joined: Mon Apr 15, 2019 5:34 pm

Re: Indentify Stakeholders Process - Change Request

Postby bhavini.barot Mon May 06, 2019 5:59 pm

This makes sense now. Thank you Manish for directing me to right place.