PMP micro learning videos Series - PMP Free Question 26: Modification in Organization Process

List of all PMP® Resources of iZenbridge, blog, slides, video, and files. All in one place now
jyotimayank
Expert
Expert
Posts: 534
Joined: Mon Mar 09, 2015 6:01 am

PMP micro learning videos Series - PMP Free Question 26: Modification in Organization Process

Postby jyotimayank Wed May 01, 2019 8:38 am

Your organization has a rule of decomposition of the work breakdown structure at a level, where the work can be done in less than a week; you planned to change this to a month for your project, what would you do next?

A. Inform the team about it
B. Request for tailoring
C. Prepare the Scope Management Plan with a one-month level WBS
D. Raise a Change Request

So the question asks what you do when you plan to modify your Organization Project Management Process.

Can you directly go ahead and plan as per your understanding of the project need?

If you think yes, you can be looking to select one of the following options
A. Inform the team about it
C. Prepare the Scope Management Plan with a one-month level WBS

We don't think that the Project Manager can decide on his own about the process; he is expected to work with stakeholders and ask for agreement. So we look at the other two options
B. Request for tailoring
D. Raise a Change Request

Tailoring is necessary because each project is unique; and it should address the competing constraints of scope, cost, etc. The issue is about process customization.
Watch this video for the correct answer.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “PMP® Resources”

Who is online

Users browsing this forum: No registered users and 0 guests