change management in adaptive

Postby ABDL1234 Wed Mar 13, 2019 4:55 am

if we have prioritized items in the backlog , and one change requested by stakeholder , plz explain how we will handle change management in adaptive ?
how we make the impact analysis for the change ?

thank you in advance
seema.sonkiya
Expert
Expert
Posts: 2296
Joined: Fri Jul 11, 2014 11:57 am

Re: change management in adaptive

Postby seema.sonkiya Wed Mar 13, 2019 9:32 am

Backlog management concept is applied in an Agile way (Adaptive Life Cycle) of delivering products, in this environment we need to address change requests which are frequently coming. And if we talk about Scrum Framework, the change management is taken care by process framework itself.

Work is delivered using frequent iterations these iteration lengths are short enough where work can be implemented without any change request and at the end of the iteration, work is shown to stakeholders, and they give the feedback. Based on feedbacks, the backlog is adapted and work for next is selected from this adapted backlog. This is the organic way of managing changes where the process framework itself takes care of changes.