Project Management Process

Postby taterarpit Mon Aug 25, 2014 7:11 pm

I was reading PMBOK and just noticed a point which says " following activities may occur during project closure " and one of the items listed is as follows ...

" Perform team member's assessments and release project resources ".

I do understand about release of resources but team member's performance assessment happens in closure or during develop project team which is part of execution. Just got confused here.

Source :- Page 58 PMBOK 5th Edition.
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Project Management Process

Postby signor_rk Tue Aug 26, 2014 5:53 am

What I understand so far is :
In Develop Project Team process , assessment for performance is done for the overall project team , whereas , in the Close Project or Phase process , it is done for individual Project Team members.
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Project Management Process

Postby namita Tue Aug 26, 2014 6:38 am

Closure is the point where team will get dismantled... team members will go back to their functional departments. Before this happens, how team members performed in the current project under you as PM is something you should do formally. I recommend going through below webinar for more insights into close project/phase process