Postby anand.sutar Sun Jan 06, 2019 2:28 am

Dear Manish Sir,
I feel, below phase wise cost estimation calculations, kindly guide.

Initiation: ROM: -25% to +75% & (while developing Project Charter) Preliminary Estimate: -15% to +50% or based on Project type, but generally between ROM or Preliminary Estimate

Planning: Budget Estimate: -10% to +25%

Execution: Calculation based on Updated "Basis of estimation"

M&C: Calculation based on Updated "Basis of estimation"

Closing: Definitive Estimate: -5 to 10%