1.Schedule baseline
2.Project schedule
3.Schedule data
What is different ?
Schedule baseline
Re: Schedule baseline
Lets look at the glossary definition of these three terms
Schedule data is base data like resource , activity , constraints , which results in project schedule, and one of the project schedule version which we pick for reference is baseline schedule, so baseline schedule is also a project schedule but not all project schedule are baselined.
Schedule Data. The collection of information for describing and controlling the schedule.
Project Schedule. An output of a schedule model that presents linked activities with planned dates, durations,
milestones, and resources.
Schedule Baseline. The approved version of a schedule model that can be changed only through formal change
control procedures and is used as a basis for comparison to actual results.
Schedule data is base data like resource , activity , constraints , which results in project schedule, and one of the project schedule version which we pick for reference is baseline schedule, so baseline schedule is also a project schedule but not all project schedule are baselined.
Re: Schedule baseline
Thank you, MR Saket
but Why Project schedule INPUT control schedule ?
but Why Project schedule INPUT control schedule ?
Re: Schedule baseline
Project Schedule is a live document , unlike the Schedule Baseline which can be updated/re-baselined only through formal Change Control procedure.
Regards ,
Ranjit
Ranjit
Re: Schedule baseline
Because control schedule looks into variance between project schedule (the current schedule which is updated based on reality ) and baseline schedule (included in project management plan ) .