I still think that the Project charter is not required for every phase. Please see the Question and explanation. Please provide your views as well .. thanks
charter-question.PNG
Charter Questions
charter-question.PNG (125.39 KiB) Viewed 1073 times

Charter_Explain.PNG
Solution
Charter_Explain.PNG (93.26 KiB) Viewed 1073 times
-----------------
Regards, Niraj
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Develop Project Charter for a new phase ? -

Postby signor_rk Tue Dec 23, 2014 8:13 am

For the 2nd Phase with new 5 Bridges , the Stakeholders might be different. So , better to cover the high level risks and project requirements in a different set of Project Charter.
Regards ,

Ranjit
kniraj
Participant
Participant
Posts: 59
Joined: Sat Oct 11, 2014 4:45 pm

Re: Develop Project Charter for a new phase ? -

Postby kniraj Tue Dec 23, 2014 12:13 pm

Thanks Ranjit, I was under the impression that Charter would define the entire project at once (all phases etc..) Identify Stakeholders could be done for every phase as you rightly mentioned.
-----------------
Regards, Niraj
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: Develop Project Charter for a new phase ? -

Postby pank_pmp Tue Dec 23, 2014 3:48 pm

I do not like this question! Where exactly it says that every phase has to be treated like a new project/sub project! It could be one major project, which includes 10 different phases. You do not create project charter for each phase just for the reason that you have different stakeholders in phases. Stakeholders can change within the phase itself, so that doesn't make sense to me!

What is the source of question?
sachinsinha
Contributor
Contributor
Posts: 187
Joined: Sun Sep 07, 2014 4:00 pm

Re: Develop Project Charter for a new phase ? -

Postby sachinsinha Tue Dec 23, 2014 6:05 pm

It cannot be Project Charter, there seems to be some ambiguity in the question.
kniraj
Participant
Participant
Posts: 59
Joined: Sat Oct 11, 2014 4:45 pm

Re: Develop Project Charter for a new phase ? -

Postby kniraj Wed Dec 24, 2014 3:20 pm

Yes, I agree.. it is confusing.. This is from pmstudy.com
-----------------
Regards, Niraj
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Develop Project Charter for a new phase ? -

Postby saket Thu Dec 25, 2014 3:44 am

In general we do not look back at project charter for modifications and whenever we discover new things like risk etc once project started we update them in project management plan (risk register etc), so when we enter in new phase and we have risk identified , we put it in Risk register not on project charter.

Change in project charter is rare and in general it is treated more like new project. Yes Identify stakeholders should be performed at every phase initiation.