On Manage project Team, Q could be wrongly phrased

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
raghu
Beginner
Beginner
Posts: 20
Joined: Wed Oct 29, 2014 2:09 pm

On Manage project Team, Q could be wrongly phrased

Postby raghu Sat Dec 20, 2014 12:55 pm

Source: www.tutorialspoint.com

The process of Manage project team uses which of the following inputs in its execution?

A. Issue Log
B. Resource Calendars
C. Activity Resource Requirements
D. Human Resource Management Plan

Answer:A
Hint: PMBOK 5, Page 257, Sec 9.4


For this question, answer should have been given as Both 'A' and 'D'. Isn't it?
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: On Manage project Team, Q could be wrongly phrased

Postby pank_pmp Sat Dec 20, 2014 3:54 pm

As per PMBOK both A and D are inputs for Manage Project Team. So I think You should avoid such questions for exam point of view!
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: On Manage project Team, Q could be wrongly phrased

Postby signor_rk Sat Dec 20, 2014 4:43 pm

Yes , it's better to avoid some questions like this.
Regards ,

Ranjit
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: On Manage project Team, Q could be wrongly phrased

Postby saket Mon Dec 22, 2014 2:15 am

Yes you are right, not to take any test question or answer as final conclusion, we need to put our PMBOK and project management knowledge in use, since PMI is going to judge us based on that.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
dipti5ece
Contributor
Contributor
Posts: 134
Joined: Tue Sep 09, 2014 8:31 am

Re: On Manage project Team, Q could be wrongly phrased

Postby dipti5ece Mon Dec 22, 2014 6:08 am

According to me both are right answers but then we must be selecting the best one.

Issue log is one of the main inputs in Manage prj team process.
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: On Manage project Team, Q could be wrongly phrased

Postby pank_pmp Mon Dec 22, 2014 6:26 am

According to me both are right answers but then we must be selecting the best one.

Issue log is one of the main inputs in Manage prj team process.


I disagree with this! PMBOK is bible for exam! Choosing "Best ones" are not direct questions and more of conditional based. For instance, which is the best/immediate OPTION is to do :) . Such questions may have couple of or may be all of the options right but one need to choose the best next approach.

This question directly referring to ITTO of Manage Project Team process.
raghu
Beginner
Beginner
Posts: 20
Joined: Wed Oct 29, 2014 2:09 pm

Re: On Manage project Team, Q could be wrongly phrased

Postby raghu Wed Dec 24, 2014 8:58 pm

Thank you Dipti for bringing a different point.

You may be wrong. But would like to know the view points here and adherence to PMBOK.
Please elaborate bit more on why you think "Issue Log" is the main input for Manage Project team process?