The activity “Ship Container” in Raj’s network diagram has an early start of day 17, a late start of day 22 and a late finish of day 37. What is the activity duration?
A.) 14 days
B.) 16 days
C.) 33 days
D.) 24days
Shant
Posts: 14
Joined: Tue Jul 22, 2014 11:25 am

Re: Question related to activity duration

Postby Shant Mon Dec 08, 2014 1:43 pm

I THINK 16 DAYS..
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Question related to activity duration

Postby signor_rk Mon Dec 08, 2014 2:41 pm

You are right Shant. Option # B) 16 days

Justification:

Activity Duration = LF - LS +1 = 37 - 22 + 1 = 16 days.