EEF Question

Postby umeshbww Wed Sep 17, 2014 11:00 pm

Jonathan has recently been hired in a company as a business improvement manager. Jonathan has been asked to reorganize the company's meetings and reporting structure. Jonathan is currently identifying all key project stakeholders. Which of the following enterprise environmental factors is least likely to be used as an input to this process?
A. Organizational culture and structure
B. Existing human resources
C. Project management information system
D. Industry standards
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
Parul
Expert
Expert
Posts: 21
Joined: Thu Aug 14, 2014 5:08 am

Re: EEF Question

Postby Parul Fri Sep 19, 2014 4:16 am

Hi Umesh,

Project Management Information System is not required when we are trying to identify Stakeholders.

Once they are Identified while planing the communication process and reporting system we will consider Project Management Information System.

Hence C
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: EEF Question

Postby umeshbww Fri Sep 19, 2014 3:14 pm

Thanks Parul.
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
bs_pani
Super Member
Super Member
Posts: 663
Joined: Mon Sep 22, 2014 3:36 pm

Re: EEF Question

Postby bs_pani Thu Dec 04, 2014 8:26 pm

I agree with Parul that we do not use PMIS for Identifying Stakeholder. But do we really use Existing human resources for Identifying Stakeholder? I do not see that as well in PMBOK Page 395.

For me both B and C is correct answer. Any though on this?
pank_pmp
Super Member
Super Member
Posts: 490
Joined: Tue Aug 05, 2014 11:04 am

Re: EEF Question

Postby pank_pmp Fri Dec 05, 2014 7:23 am

Existing Human Resources may include team lead, expert, Middle Management, Sr. Management, Sponsors, SME and moreover their hierarchy is also important. I think this understanding is important in identifying stakeholders.
bs_pani
Super Member
Super Member
Posts: 663
Joined: Mon Sep 22, 2014 3:36 pm

Re: EEF Question

Postby bs_pani Fri Dec 05, 2014 5:07 pm

Pankaj,

I understand you point. But if a pre existing resource is so important to project then he will be pre assigned to the project. If you take the existing human resource then everyone in the company will be stake holder to the project which does not look correct to me.