Question on change?

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
nagarwal
Participant
Participant
Posts: 60
Joined: Sun Jun 22, 2014 8:34 am

Question on change?

Postby nagarwal Fri Aug 29, 2014 11:24 am

The deliverables as well as the schedule baselines of your project have been changed three times. Which of the following is MOST LIKELY the cause of the changes?
 
1. The lack of clear instructions from project sponsor.
 
2. Incomplete project management plans.

3. The lack of a signed-off project charter.

4. Incomplete project scope management plans
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Question on change?

Postby umeshbww Fri Aug 29, 2014 6:42 pm

I will choose option 2. Incomplete project management plans

Project Charter is high level documents and don't have detailed deliverables or schedule baseline.

Although incomplete scope management plan can also have ripple effect in changing deliverables and schedule baselines.
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Question on change?

Postby signor_rk Sat Aug 30, 2014 8:03 am

The best possible Option is the Option # 1 1. The lack of clear instructions from project sponsor. The other options follow thereafter.
 
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question on change?

Postby namita Tue Sep 02, 2014 7:40 am

What is the source of this question?
nagarwal
Participant
Participant
Posts: 60
Joined: Sun Jun 22, 2014 8:34 am

Re: Question on change?

Postby nagarwal Tue Sep 02, 2014 10:37 am

passionate pmp free questions
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Re: Question on change?

Postby taterarpit Sat Sep 06, 2014 4:47 am

what is the correct answer?
User avatar
saket
Site Admin
Site Admin
Posts: 3125
Joined: Sat Dec 07, 2013 10:37 pm

Re: Question on change?

Postby saket Sat Sep 06, 2014 5:21 am

Its not necessary to match your thought process with each mock test, finally the PMI is the one who is gona take final call , each writer (including me :-) ) may have some different view for things

The deliverables as well as the schedule baselines of your project have been changed three times. Which of the following is MOST LIKELY the cause of the changes?


Change in deliverable mean unstable scope, which in turn resulting in change of schedule, since it is getting baseline which shows PM and team is doing replanning and sponsor is approving the replanning again and again.

Now look for options
1. The lack of clear instructions from project sponsor.
 
Could be the reason that is why he is ok for replanning.

2. Incomplete project management plans.

I am not getting any clue where it shows that project management plan was incomplete and that is resulting in change, rather question is saying we have baselines

3. The lack of a signed-off project charter.


No reason to believe this

4. Incomplete project scope management plans


This could be the reason since the change is happening in scope , but since we have approval of baseline i prefer selective option 1.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 10 guests