Question

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Question

Postby taterarpit Wed Aug 27, 2014 5:20 pm

When do you perform stakeholder analysis?

A.When defining the project scope
B.When developing the project charter
C.When creating the project management plan
D.When putting changes through change control
umeshbww
Contributor
Contributor
Posts: 168
Joined: Fri Aug 15, 2014 3:02 pm

Re: Question

Postby umeshbww Wed Aug 27, 2014 10:00 pm

A.When defining the project scope
Before you define project scope - you need to collect requirements from Stakeholders(Sponsor/Customers etc); Stakeholder Register (output of Stakeholder analysis tool in Identify Stakeholders) acts as input for collecting requirements
B.When developing the project charter (project charter acts as input for identifying stakeholders)
C.When creating the project management plan
D.When putting changes through change control (its part of monitor/controlling process group)

I am confirmed B and D are definitely not possible.
GOAL : PMP Certified by 24th Sept 2014 -- ACCOMPLISHED