CSM Forum Banner

Question....

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Question....

Postby taterarpit Tue Aug 19, 2014 7:31 am

Question:- A team member is trying to pull a team member off the project to do other work. Who is key person for this situation
A. Project Manager
B. Team
C. Sponsor
D. Functional Manager
signor_rk
Contributor
Contributor
Posts: 182
Joined: Wed Jun 18, 2014 3:47 pm

Re: Question....

Postby signor_rk Tue Aug 19, 2014 8:01 am

It might be the Functional Manager who is instructing the 1st Team member to pull the 2nd Team member out off the Project to perform another work. So Option # D , i.e., Functional Manager ... :)
Regards ,

Ranjit
namita
Super Member
Super Member
Posts: 502
Joined: Wed Dec 11, 2013 10:25 am

Re: Question....

Postby namita Tue Aug 19, 2014 8:18 am

this question is very open ended. Please share the source.

I would say it depends in kind of organization structure. Both PM and FM can be key depending on Org
taterarpit
Contributor
Contributor
Posts: 111
Joined: Sat Jul 26, 2014 6:42 pm

Re: Question....

Postby taterarpit Tue Aug 19, 2014 8:50 am

Thanks Namitha...thanks for the answer ...in this question i am talking about Matrix ORG....however, even i thought answer would be FM but answer is TEAM...which is not at all correct answer in my opinion...

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: No registered users and 14 guests