Hi ,

Please can you let me know , cost for implementing CR will be taken from contingency reserves or its an additional approved cost which will be added to cost baseline ?


Regards
Asim Ali
puja.pajan1984
Posts: 19
Joined: Wed Nov 08, 2017 4:47 am

Re: Cost of change request implementation

Postby puja.pajan1984 Sat Mar 03, 2018 9:34 pm

Cost of quality is a tool and technique used in determining budget. COQ includes cost for non conformance (Defect repair/ rework etc) or conformance (preventive, corrective action), so In my opinion, it should be part of cost baseline. But if a change is implemented as part of risk response or workaround only then it can be taken from contingency reserve.

Manish sir please comment.
seema.sonkiya
Expert
Expert
Posts: 2104
Joined: Fri Jul 11, 2014 11:57 am

Re: Cost of change request implementation

Postby seema.sonkiya Wed Apr 18, 2018 7:49 am

Sorry for the delay in the response.

Please can you let me know , cost for implementing CR will be taken from contingency reserves or its an additional approved cost which will be added to cost baseline ?


No change request is needed if we are using contingency reserve. The contingency reserve is part of cost baseline, and if something is part of the baseline, then no CR is needed.