Postby asimali Thu Mar 01, 2018 6:47 pm

Hi ,

Which of the following is true statement about risks?

A- If a risk is identified in a risk response plan, then that means that risk has already happened.
B- Once a risk has happened, you refer to the risk management plan to determine what action needs to be taken.
C - A risk that was not planned but has happened is called a trigger.
D- Risk identification happens in all the phases of the project.


Regards
Asim Ali
nagak7079@gmail.com
Posts: 9
Joined: Thu Mar 02, 2017 5:14 pm

Re: Risk Identification

Postby nagak7079@gmail.com Thu Mar 01, 2018 10:59 pm

D- Risk identification happens in all the phases of the project.

identify risk process got input from all processes.
Prembalaji
Participant
Participant
Posts: 69
Joined: Wed May 10, 2017 1:38 pm

Re: Risk Identification

Postby Prembalaji Fri Mar 02, 2018 2:55 am

A- If a risk is identified in a risk response plan, then that means that risk has already happened.
Risk response plan will be created irrespective of the Risk Occurrence

B- Once a risk has happened, you refer to the risk management plan to determine what action needs to be taken.
Once a risk has happened, you refer to Risk Response plan and not to Risk Mgmgt Plan

C - A risk that was not planned but has happened is called a trigger.
An event or a situation that leads to the Risk is called a Trigger

D- Risk identification happens in all the phases of the project.
BINGO, the right answer
Cheers,
PJ