Communication management

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
puja.pajan1984
Posts: 19
Joined: Wed Nov 08, 2017 4:47 am

Communication management

Postby puja.pajan1984 Wed Feb 28, 2018 11:15 am

Joy is creating consolidated weekly status report of his project, which of the following will not be useful input for this process?

1.Communications Management plan
2.Work performance Reports
3.List of Stakeholders
4.Government regulations

Answer - 3
Quampus Explanation - Stakeholder register is not needed as an input to manage communication, Government regulations are part of Enterprise Environmental factors which may influence the weekly report creation process.

My question - Is Stakeholder list not an input because its already a part of communication Management Plan?

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: Google [Bot] and 13 guests