Got following question:

Final acceptance and signed off of the of Deliverables handed over by the contractor to the customer happens in Control Procurement or Close Procurement phase ?
manishpn
Expert
Expert
Posts: 2509
Joined: Sat Jan 04, 2014 3:55 pm

Re: Final acceptance and signed off of the of Deliverables

Postby manishpn Tue Feb 27, 2018 5:31 am

seema.sonkiya wrote:Got following question:

Final acceptance and signed off of the of Deliverables handed over by the contractor to the customer happens in Control Procurement or Close Procurement phase ?


in real world, final acceptance can happen in control or close procurement
however for PMP exam keep it simple and only consider it happening in close procurement.
Close procurement is primarily focused on formally closing the contract in all aspect, commercial , administrative and delivery
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 6 guests