One day bangalore & kolkata

Manish sir pls help--CR versus project document updates

Exclusive forum for iZenBirdge PMP® clients
ajaynit
Contributor
Contributor
Posts: 110
Joined: Thu Dec 07, 2017 5:35 pm

Manish sir pls help--CR versus project document updates

Postby ajaynit Sun Jan 07, 2018 5:05 pm

many processes have output as CR, mostly control and execution processes and only one from planning (plan Procurement mngmt).

CR ultimately leads to Project management plan (relevant subsidiary plan) update.
ideally this way...

Process-->Raise CR--> Perform Integrated Change control --> Approved CR--> Update Plan.

my question:
lets take case of plan risk response process. this triggers changes in project management plan then why not is this done through formal change request management??

random thoughts in my mind:
because Project mngmt plan is not yet approved/frozen yet?

if my thoughts are making sense then why CR as a o/p of plan procurement when it might be the case that project mngmt plan is not yet approved in this case as well?
manishpn
Expert
Expert
Posts: 2442
Joined: Sat Jan 04, 2014 3:55 pm

Re: Manish sir pls help--CR versus project document updates

Postby manishpn Sun Jan 07, 2018 6:13 pm

ajaynit wrote:many processes have output as CR, mostly control and execution processes and only one from planning (plan Procurement mngmt).

CR ultimately leads to Project management plan (relevant subsidiary plan) update.
ideally this way...

Process-->Raise CR--> Perform Integrated Change control --> Approved CR--> Update Plan.

my question:
lets take case of plan risk response process. this triggers changes in project management plan then why not is this done through formal change request management??

random thoughts in my mind:
because Project mngmt plan is not yet approved/frozen yet?

Yes thats true in case PMP is not baselined and approved we do not need a CR to update the plan,
do remember that since the process is iterative, plan risk response could also happen after the PMP is baselined and then in that case there is a need of CR to change baseline plan of PMP


if my thoughts are making sense then why CR as a o/p of plan procurement when it might be the case that project mngmt plan is not yet approved in this case as well?

Again plan procurement can also happen after PMP is approved, as a decision to procure can happen anytime in the project

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
ajaynit
Contributor
Contributor
Posts: 110
Joined: Thu Dec 07, 2017 5:35 pm

Re: Manish sir pls help--CR versus project document updates

Postby ajaynit Sun Jan 07, 2018 6:25 pm

thanks Manish sir, sorry bothering you too much during your holidays..
manishpn
Expert
Expert
Posts: 2442
Joined: Sat Jan 04, 2014 3:55 pm

Re: Manish sir pls help--CR versus project document updates

Postby manishpn Tue Jan 09, 2018 7:31 am

No issues I will reply when I have time.

Apologies or delays in response
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
ajaynit
Contributor
Contributor
Posts: 110
Joined: Thu Dec 07, 2017 5:35 pm

Re: Manish sir pls help--CR versus project document updates

Postby ajaynit Thu Jan 11, 2018 5:45 am

i got another or may be same query on same line while re-visiting risk management area:

i interpret that PMBOK ITTO table assumes that when we are doing risk management at first then scope baseline is ready but no other baselines are ready yet.

Plan risk response says that due to this risk planning there will be "project documents update" like scope baseline (PMBOK ,Page 347). my question is updates to baseline should be considered only through CR? if so then plan risk response process should generate CR? if it should generate CR then why is there no mention of CR as output of this process in pmbok?

i am not able make peace with whole cycle here.. if someone can illustrate an generic example of risk , plan risk response, project document update process then it would be great help..
manishpn
Expert
Expert
Posts: 2442
Joined: Sat Jan 04, 2014 3:55 pm

Re: Manish sir pls help--CR versus project document updates

Postby manishpn Thu Jan 25, 2018 7:37 am

ajaynit wrote:i got another or may be same query on same line while re-visiting risk management area:

i interpret that PMBOK ITTO table assumes that when we are doing risk management at first then scope baseline is ready but no other baselines are ready yet.
There is no prescribed sequence however it makes sense to do risk response, quality planning , etc before baselining

Plan risk response says that due to this risk planning there will be "project documents update" like scope baseline (PMBOK ,Page 347). my question is updates to baseline should be considered only through CR? if so then plan risk response process should generate CR? if it should generate CR then why is there no mention of CR as output of this process in pmbok?
In first pass when the scope is not baselined we do not need a CR however if PM is doing risk plan risk responses after baselining and there is impact on any of the baseline then we will need a CR and as I have mentioned many times before PMBOK is not a rulebook its a guide, so if one of the output is missing , it does not mean a PM cannot generate the output through a given process.

i am not able make peace with whole cycle here.. if someone can illustrate an generic example of risk , plan risk response, project document update process then it would be great help..
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 5 guests