Postby Prembalaji Mon Dec 18, 2017 2:11 am

You are assigned as the PM for an Highy important [project in your organization. You have only been given 10 resources and there are no more resources available in the company, The Project should be completed in a period which is half the time that will take you to complete the project with the available resources. Due to the Projects high priority, management does not accept any change in the Projects required completion date. What will you do in this situation

1.Relax some Quality Requirements
2.Provide the available resources with some training to increase their performance
3.Look for any part of the scope that can be cut
4.Ask your available resources to work overtime
Cheers,
PJ
shanthi priya
Posts: 1
Joined: Wed May 10, 2017 10:34 am

Re: Tricky Question

Postby shanthi priya Tue Dec 19, 2017 12:47 pm

May be its Option 4.
rahul.kanugo
Participant
Participant
Posts: 69
Joined: Tue May 17, 2016 4:42 pm

Re: Tricky Question

Postby rahul.kanugo Tue Dec 19, 2017 3:17 pm

1.Relax some Quality Requirements :- Highly important project Quality cant be compromised
2.Provide the available resources with some training to increase their performance .(Is not measurable )
3.Look for any part of the scope that can be cut (No scope for any change)
4.Ask your available resources to work overtime(Only option left)

Answer as D
manishpn
Expert
Expert
Posts: 2448
Joined: Sat Jan 04, 2014 3:55 pm

Re: Tricky Question

Postby manishpn Thu Dec 21, 2017 5:28 pm

asking resources to work over time ( on a continuous basis) is against PMI ethics

now think what could be the option
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 276
Joined: Sun Feb 26, 2017 6:06 am

Re: Tricky Question

Postby nazrulq Fri Dec 22, 2017 12:40 am

Asking for overtime and work in the weekends( Not Mentioned) are against PMI Code of Ethics.
On job Training ( Not mentioned PMP exam should be clear that ) is the possible right choice!
Sometimes made up an answer just missed some information which can clear the right choice.
In that case, PMI should scrutinize the answer and questions with special attention.
dmegha
Posts: 4
Joined: Fri Sep 15, 2017 1:45 am

Re: Tricky Question

Postby dmegha Fri Dec 22, 2017 5:55 am

ANS: 3 (Cut the scope)

Time and Cost are constraints, hence, PM should priorities the requirements and deliver only the high priority requirements
Last edited by dmegha on Fri Dec 22, 2017 8:57 am, edited 1 time in total.
Prembalaji
Participant
Participant
Posts: 61
Joined: Wed May 10, 2017 1:38 pm

Re: Tricky Question

Postby Prembalaji Fri Dec 22, 2017 6:07 am

yes , the answer provided was to CUT the SCOPE .

But im not able to make peace with the answer .
Cheers,
PJ
dmegha
Posts: 4
Joined: Fri Sep 15, 2017 1:45 am

Re: Tricky Question

Postby dmegha Fri Dec 22, 2017 9:02 am

Use the process of elimination.

1.Relax some Quality Requirements - Quality cannot be compromised, hence eliminated
2.Provide the available resources with some training to increase their performance - Competancy is not the issue, hence eliminated
3.Look for any part of the scope that can be cut
4.Ask your available resources to work overtime - PMI doesn't promote overtime.

Hence, C
sandeep.gulvadi
Posts: 2
Joined: Tue Oct 31, 2017 12:53 am

Re: Tricky Question

Postby sandeep.gulvadi Sat Dec 23, 2017 6:07 am

From the above ans shall be 4.

May comes under PMBOK Schedule compression, crashing - to shorten the schedule duration, overtime can be approved when activities are on critical path.

Regards
Sandeep
ankurece012
Posts: 7
Joined: Fri Oct 27, 2017 8:00 pm

Re: Tricky Question

Postby ankurece012 Wed Jan 03, 2018 8:21 pm

I believe Option D will be the right choice.
I was also thinking about option B, but that again requires an additional budget for training and I didn't see any data that tells us about the reserve that project had planned for training.