Risk Response - Q1

Postby Prembalaji Sat Dec 09, 2017 4:00 am

For a project that you are managing, you decide to respond to an identified risk by clarifying requirements and obtaining information very early in the project. This strategy is called as?

Avoid
Transfer
Mitigate
Accept
Cheers,
PJ
manishpn
Expert
Expert
Posts: 2474
Joined: Sat Jan 04, 2014 3:55 pm

Re: Risk Response - Q1

Postby manishpn Sun Dec 17, 2017 10:52 am

Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
suresi00
Contributor
Contributor
Posts: 150
Joined: Mon Nov 20, 2017 4:05 pm

Re: Risk Response - Q1

Postby suresi00 Sun Dec 17, 2017 11:18 am

So here we are reducing risk exposure by understanding the requirements, After reading the blog it seems to me that it is an example of mitigation. Is my answer right?
dmegha
Posts: 4
Joined: Fri Sep 15, 2017 1:45 am

Re: Risk Response - Q1

Postby dmegha Fri Dec 22, 2017 9:03 am

Mitigate
pankaj
Posts: 1
Joined: Sun Nov 05, 2017 7:16 am

Re: Risk Response - Q1

Postby pankaj Fri Dec 22, 2017 9:12 am

Mitigate