Postby nazrulq Sat Sep 23, 2017 10:21 pm

Workaround is the negative risk for which the project is not planned for. It is managed by contingency reserve.
My question all risks are in response to plan risk response ( Fallback plan, residual risk, secondary risk) but why
workaround is done in control risk process why not planning as risk response. Is that only not for planned early!

Can somebody explain!

Thanks.
manishpn
Expert
Expert
Posts: 2209
Joined: Sat Jan 04, 2014 3:55 pm

Re: Workaround

Postby manishpn Sun Sep 24, 2017 11:21 am

I have explained this before many times,

Workaround are NOT PLANNED, its used if your initial response is not effective enough.

There workarounds are not planned in planning stage
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
nazrulq
Contributor
Contributor
Posts: 237
Joined: Sun Feb 26, 2017 6:06 am

Re: Workaround

Postby nazrulq Thu Oct 05, 2017 5:36 pm

As there is no execution phase for the Risk Management in PMBOK5 it should be in Monitor and control. But According to PMBOK6 it would be in execution phase! We are safe till March 26,2018! :D :D
manishpn
Expert
Expert
Posts: 2209
Joined: Sat Jan 04, 2014 3:55 pm

Re: Workaround

Postby manishpn Tue Oct 17, 2017 7:36 pm

:)
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/