residual risk and secondary risk difference

Here we discuss iZenBridge free questions, which are high in quality with good explanations. We invite you to participate in these questions; it will be fun filling for the exam preparation.
Pawanrec
Posts: 7
Joined: Mon Jul 31, 2017 7:31 am

residual risk and secondary risk difference

Postby Pawanrec Sat Sep 30, 2017 12:44 am

Hi
i understand that
residual risk: are existing risk for which we already planned risk response but those are not completely removed & still present with less probability/impact ( may be shifted to watch list)
secondary risk: we execute risk response plan for a particular risk and with implementation of risk response plan another new risk generated is called secondary risk

please advise understanding is correct &
some examples requested for better understanding on it
nazrulq
Contributor
Contributor
Posts: 235
Joined: Sun Feb 26, 2017 6:06 am

Re: residual risk and secondary risk difference

Postby nazrulq Thu Oct 05, 2017 3:56 am

I do n't think residual risks are low priority risks could be the moderately priority too. Those risks remain after mitigation plan.Only low priority can be placed in Watchlist.

I think Manish Can clarify more!
manishpn
Expert
Expert
Posts: 2196
Joined: Sat Jan 04, 2014 3:55 pm

Re: residual risk and secondary risk difference

Postby manishpn Sat Oct 07, 2017 5:55 pm

please refer to thread with discussion on this
viewtopic.php?f=11&t=5054&p=18761&hilit=residual+risk#p18758

there are many more discussions that have happened in this this regards on forum
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “iZenBridge PMP Open Questions”

Who is online

Users browsing this forum: No registered users and 0 guests