Oliver 175 - 81st Question

Postby jyotimayank Thu Jan 19, 2017 1:02 pm

Question 81

You are going to take over a new project as the project manager in an enterprise unknown to you. What should you investigate during the chartering process?

A. Enterprise environmental factors
B. Project management plan
C. Project risk register
D. Team performance reports
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
rahul.kanugo
Beginner
Beginner
Posts: 40
Joined: Tue May 17, 2016 4:42 pm

Re: Oliver 175 - 81st Question

Postby rahul.kanugo Sat Jan 28, 2017 10:24 am

answer is A,,,,, am i right
jyotimayank
Expert
Expert
Posts: 504
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 81st Question

Postby jyotimayank Mon Jan 30, 2017 5:10 am

Yes you are right Rahul :) . The correct answer is option A.


Refer pages 29 and 70 of PMBOK® Guide 5th Edition

As defined in definition EEF are conditions which are given, they are coming from an environment, the project team has no control over them, but project team needs to understand them well to successfully manage the project. Here are a few examples
1. Organization if following matrix organization structure, where as Development function head is more powerful than other function heads.
2. The organization is using the XYZ project management system, project reports will be taken out of it for management reviews.


You can refer to the following link for more insight of this topic
http://www.izenbridge.com/blog/enterpri ... ss-assets/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd