While planning for a critical project delivery, you want to give yourself a few extra hours from budgeted time for a construction and testing phase to account for problems with unavailability of team resources for any reasons or delays in delivery. This scenario can be BEST described as ___

Padding
Risk acceptance
Reserve time or contingency
Mitigation
coolpmp69
Contributor
Contributor
Posts: 282
Joined: Mon Nov 17, 2014 8:55 pm

Re: Risk management

Postby coolpmp69 Wed Oct 07, 2015 2:01 pm

My Answer -Reserve time or contingency
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Risk management

Postby ujjal_show Wed Oct 07, 2015 7:52 pm

And why its not Risk acceptance (active) ?
vivek3377
Super Member
Super Member
Posts: 391
Joined: Thu Sep 10, 2015 2:32 am

Re: Risk management

Postby vivek3377 Wed Oct 07, 2015 8:47 pm

As per PMBOK -
Risk Acceptance is a risk response strategy whereby project team decides to acknowledge the risk and not take any action unless the risk occurs.
It also mentions that The most common active risk acceptance strategy is contingency reserves. So just keep some time, cost or resources buffer to cover for the known risk with unknown response.
If you have 'Contingency Reserves' as option specifically mentioned, then go with that option, rather than a generic 'Risk Acceptance' option.
But I have my doubts about this. How can one estimate the reserves required, if they don't know what has to be done if the risk arises? I mean, how would one estimate that buffer is sufficient to handle the risk contingency or not? Or is it just a certain percentage of time, cost and effort kept aside, and decide on what to do with them when the risk rises? Of course, there will certainly be some ground rules about what percentage can be kept as buffer, but still.... :?
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Risk management

Postby ujjal_show Wed Oct 07, 2015 9:37 pm

Yes, you are correct. contingency is more specific.

And risk acceptance /contingency does not mean we didn't done any homework, remember plan risk response done after analysed, prioritized and simulation process. where how much time or cost is require is already been identified in analyzing (Probability-Impact) the risk.

also note acceptance strategy is applied for non critical/ low impact risk, so that is also another way of saying "It already analysed and cost / time impact calculated.

the same logic applied to passive acceptance also.
vivek3377
Super Member
Super Member
Posts: 391
Joined: Thu Sep 10, 2015 2:32 am

Re: Risk management

Postby vivek3377 Thu Oct 08, 2015 3:13 am

Good point. And low risks are generally added to the watch list, without active risk response planning - apart from contingency planning.
So we mutually enhance our knowledge on this topic by sharing the thoughts on this forum! Really a good avenue to collaborate!
Thanks iZenBridge!

Return to “PMP® Open Forum”

Who is online

Users browsing this forum: Bing [Bot] and 4 guests