CSM Forum Banner

Oliver 175 - 82nd Question

jyotimayank
Expert
Expert
Posts: 502
Joined: Mon Mar 09, 2015 6:01 am

Oliver 175 - 82nd Question

Postby jyotimayank Thu Jan 19, 2017 1:05 pm

Question 82

A project was budgeted at $1,000,000. Meanwhile, the project is executed, and the following current figures have been assessed:
PV: $500,000
EV: $450,000
AC: $550,000
Assuming that the cost variance was caused by one-time cost drivers, which are no more effective, what estimate at completion (EaC) can you derive from these figures?
A. $900,000
B. $1,000,000
C. $1,100,000
D. $1,222,222
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
Avishek_0210
Posts: 1
Joined: Sat Feb 25, 2017 3:46 pm

Re: Oliver 175 - 82nd Question

Postby Avishek_0210 Sun Mar 26, 2017 3:57 pm

Using , EAC = AC+(BAC-EV) .. One time Variation..
EAC=550000 + (1000000-450000)
=550000+550000
=11000000

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest