Question 74

While executing a project, you sense a slightly negative attitude in your team. Which type of document do you now need, among others, to better understand and then be able to improve the situation?

A. Project charter
B. Team performance assessments
C. Cost baseline
D. Statement of work
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
jyotimayank
Expert
Expert
Posts: 499
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 74th Question

Postby jyotimayank Tue Jan 17, 2017 11:48 am

The correct answer is option B.

Refer to page 279 of PMBOK® Guide 5th Edition

Team performance assessments involves determining a team’s effectiveness. As a result of positive team-building experiences, you’ll see individuals improving their skills, team behaviors and relationships improving, conflict resolutions going smoothly, and team members recommending ways to improve the work of the project
Assessing effective team characteristics help the project manager to determine where (or whether) the project team needs improvements.
Manage Project Teams involves tracking and reporting on project team member performance.

You can refer to the following link for more insight of this topic

http://www.izenbridge.com/videogallery/ ... 3-pmbok-5/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest