Question 69

In configuration management, which of the following is necessary to maintain the integrity of baselines?

A. Analyzing variances by comparing baseline information with actual project data.
B. Releasing only approved changes for incorporation into products or services.
C. Ensuring that team members adhere to a code of ethical conduct and behavior.
D. Ensuring transparency across all project management processes and activities.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
sarthy
Beginner
Beginner
Posts: 25
Joined: Sun Feb 22, 2015 2:44 pm

Re: Oliver 175 - 69th Question

Postby sarthy Fri Jan 13, 2017 11:54 am

Obviously B, to maintain baseline project manager must ensure that only approved changes must be implemented.
jyotimayank
Expert
Expert
Posts: 499
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 69th Question

Postby jyotimayank Mon Jan 16, 2017 7:34 am

Yes Sarthy the correct answer is option B.


Refer to page 96 of PMBOK® Guide 5th Edition

The purpose of the contract change control system is to establish a formal process for submitting change requests. It documents how to submit changes, establishes the approval process, and outlines authority levels. It includes a tracking system to number the change requests and record their status. The procedures for dispute resolution are spelled out in the contract change control system as well.
Configuration management is generally a subsystem of the project management information system. It involves managing approved changes and project baselines.
A change control board (CCB) is established to review all change requests. The board is given the authority to approve or deny change requests as defined by the organization. It’s important that its authority is clearly defined and that separate procedures exist for emergency changes. All the changes should be reviewed, and the project management plan should be updated to reflect the approved changes, so as to keep the integrity of scope baseline. Depending on the nature of the changes, the project manager, stakeholders, or sponsor (or some combination) should review and approve the changes.


You can refer to the following link for more insight of this topic

PMP® Exam Series – Change request, Corrective Actions, and Preventive actions

http://www.izenbridge.com/blog/pmp-exam-series-change/
Integrated Change Control – Sequence of Change Request

http://www.izenbridge.com/blog/integrat ... e-request/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: No registered users and 1 guest