CSM Forum Banner

Oliver 175 - 67th Question

jyotimayank
Expert
Expert
Posts: 502
Joined: Mon Mar 09, 2015 6:01 am

Oliver 175 - 67th Question

Postby jyotimayank Tue Jan 10, 2017 11:54 am

Question 67

Your management announced that they want to put you on a stretch assignment.
In this situation, you should consider that…

A. …a stretch assignment is going beyond your qualifications right from the start. Whatever your education, knowledge and skills are, you cannot fail personally. Congratulations.
B. …key stakeholders must have timely and complete information regarding your qualifications to make decisions regarding your suitability for the assignment.

C. …stretch assignments bear an increased risk of failure, and this is rarely outweighed by the learning and development experience expected to come with the assignment.
D. …you should avoid the increased hassle coming with the assignment. It will not be enough for you to simply satisfy requirements and achieve objectives. You will have to learn a lot.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
jyotimayank
Expert
Expert
Posts: 502
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 67th Question

Postby jyotimayank Tue Jan 17, 2017 11:06 am

The correct answer is option B

Reference: PMI Code of Ethics and Professional Conduct

PMI members have determined that honesty, responsibility, respect and fairness are the values that drive ethical conduct for the project management profession. PMI’s Code of Ethics and Professional Conduct applies those values to the real-life practice of project management, where the best outcome is the most ethical one.

You can refer to the following link for more insight of this topic

https://www.pmi.org/about/ethics/code
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd