Question 58

What is not true for change requests?

A. Change requests should always be handled in a controlled and integrative fashion.
B. Change requests surpassing the formal change control processes can lead to scope creep.
C. Professionally managed, change requests can help improving a project and resolving emerging problems.
D. Change requests are always a sign of bad planning and should be avoided therefore.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
sarthy
Beginner
Beginner
Posts: 25
Joined: Sun Feb 22, 2015 2:44 pm

Re: Oliver 175 - 58th Question

Postby sarthy Tue Jan 10, 2017 7:38 am

Obviously D, change request cannot be the because of bad planning, it can be due to many reasons like some legal and complaince changes etc
jyotimayank
Expert
Expert
Posts: 494
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 58th Question

Postby jyotimayank Tue Jan 10, 2017 11:21 am

Yes Sarthy the correct answer is option D.
Change Request is a very sensitive term in the Project Management. In spite of you working hard to complete your project as per scope, schedule and cost as a project manager, inevitable thing always occurs which is referred to as a Change.
Refer to page 94, 136 (5.6) of PMBOK® Guide 5th Edition

As a result of working through activities and producing your product, service, or result, you
will inevitably come upon things that need to be changed. Changes can also come about from stakeholder requests, external sources, technological advances, and so on. These change requests might encompass schedule, scope, requirement, or resource changes. The list really could go on. Your job as project manager, if you choose to accept it, is to collect the change requests and make determinations about their impact on the project.


You can refer to the following link for more insight of this topic

http://www.izenbridge.com/blog/pmp-exam-series-change/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: No registered users and 2 guests