Oliver 175 - 50th Question

Postby jyotimayank Thu Dec 29, 2016 10:40 am

Question 50

In general, processes of configuration management do not include…

A. …identification and documentation of system or item characteristics.
B. …controlling changes to these characteristics in an integrative fashion.
C. …documenting and auditing changes and the implementation status.
D. …assigning responsibilities for change control and documentation.
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd
sarthy
Beginner
Beginner
Posts: 25
Joined: Sun Feb 22, 2015 2:44 pm

Re: Oliver 175 - 50th Question

Postby sarthy Thu Jan 05, 2017 11:02 am

D , assigning responsibilities for change control and documentation.
jyotimayank
Expert
Expert
Posts: 516
Joined: Mon Mar 09, 2015 6:01 am

Re: Oliver 175 - 50th Question

Postby jyotimayank Thu Jan 05, 2017 11:12 am

Yes the correct answer is option D.

Refer to page 532 of PMBOK® Guide 5th Edition

Change control systems are a subset of the configuration management system. Change requests should be approved by the CCB, but in the case of an emergency, change requests may be approved by the project manager in accordance with the process outlined in the configuration management system. The project team might have discretion to approve changes within certain parameters without CCB approval. It includes documentation, tracking systems and defined approval levels necessary for authorizing and controlling changes.

You can refer to the following link for more insight of this topic
http://www.izenbridge.com/videogallery/ ... anagement/
Jyoti Gupta
PMP Mentor & Coach

iZenbridge Consultancy Pvt Ltd

Return to “Oliver 175 PMP Questions”

Who is online

Users browsing this forum: Google [Bot] and 2 guests